Earned Value Formulas for the PMP Exam: A One-Page Cheat Sheet

Table of Contents

Short answer. The earned value formulas PMP candidates need: CV = EV – AC, CPI = EV / AC, SV = EV – PV, SPI = EV / PV, EAC = BAC / CPI when current cost performance continues, ETC = EAC – AC, VAC = BAC – EAC and TCPI = (BAC – EV) / (BAC – AC). A variance below 0 or an index below 1 is bad. PMI’s July 2026 outline does not use the words “earned value”, but it asks you to analyze financial and schedule variation and to measure project metrics. Checked against PMI on November 25, 2026.

Written by the AgileFever editorial team. Facts checked on November 25, 2026 against the official pages of the organizations named in this post. AgileFever sells training for some of the topics covered here, and we say so wherever it applies. Formulas and terms follow PMI’s earned value guidance. Every worked example and practice question is our own illustrative example, and every number in it was calculated and double-checked.

Here are the earned value formulas PMP candidates should know, one table of what each result means, four worked cases, a rule for picking the right forecast and six practice questions. It pairs with our PMP exam format guide and our critical path worked examples, which cover the other calculation topic.

Is earned value on the July 2026 PMP outline?

We searched the full text of PMI’s July 2026 Exam Content Outline (the cover says July 2026 PMP Certification Exam Update, and the page footers say revised 11 August 2026) on November 25, 2026.

What we looked for What the outline says
The words “earned value” or “EVM” Not present
Any formula or count of calculation questions Not present
Process Task 6, “Plan and manage finance” Enablers include “Plan spend tracking throughout the project life cycle” and “Monitor financial variations and work with the governance process”
Process Task 8, “Plan and manage schedule” Enablers include “Baseline a project schedule” and “Analyze schedule variation”
Process Task 9, “Evaluate project status” Enablers include “Assess current progress” and “Measure, analyze, and update project metrics”

Source: PMI Project Management Professional Examination Content Outline, July 2026 update, read November 25, 2026.

So PMI does not name earned value. It does name the work earned value does: tracking spend against a baseline, analyzing cost and schedule variation, and reporting status with metrics. Treat the earned value formulas PMP prep teaches as a tool for scenario questions, not as a promise of calculation questions. PMI’s August 31, 2026 blog on earned value uses the terms and core formulas below, and PMI lists a 150-page Standard for Earned Value Management from February 2020.

Earned value formulas PMP candidates need on one page

All the earned value formulas PMP questions use start from three numbers and one total. Planned value (PV) is the budgeted cost of the work scheduled by now. Earned value (EV) is the budgeted value of the work done. Actual cost (AC) is what you spent. Budget at completion (BAC) is the total approved budget. Older material calls PV, EV and AC by BCWS, BCWP and ACWP. EV is percent complete times BAC: a $200,000 project 30% done has EV of $60,000.

Measure Formula Question it answers Example 1 result
Planned value (PV) Planned % complete x BAC Work planned by now $80,000
Earned value (EV) Actual % complete x BAC Work done $60,000
Actual cost (AC) Recorded spend to date Spend so far $75,000
Cost variance (CV) EV – AC Over or under budget -$15,000
Schedule variance (SV) EV – PV Ahead or behind plan -$20,000
Cost performance index (CPI) EV / AC Value per dollar spent 0.80
Schedule performance index (SPI) EV / PV Work done vs work planned 0.75
Estimate at completion (EAC) BAC / CPI, plus 3 variants below Final cost forecast $250,000
Estimate to complete (ETC) EAC – AC Spend still to come $175,000
Variance at completion (VAC) BAC – EAC Forecast gap to budget -$50,000
TCPI to BAC (BAC – EV) / (BAC – AC) Efficiency needed for original budget 1.12
TCPI to EAC (BAC – EV) / (EAC – AC) Efficiency needed for revised EAC 0.80

Illustrative example 1: BAC $200,000, 40% planned, 30% done, AC $75,000, EAC from BAC / CPI. Formulas as PMI states them in its August 31, 2026 blog, plus the standard PMP variants.

What CPI and SPI tell you

Result Cost (CV, CPI) Schedule (SV, SPI)
Variance below 0, index below 1 Over budget Behind plan
Variance exactly 0, index exactly 1 On budget On plan
Variance above 0, index above 1 Under budget Ahead of plan

Read the two indices together. The pattern suggests a cause, which you still have to check.

CPI SPI Typical reading
Below 1 Below 1 Late and over budget. Rework, weak estimates or scope growth
Below 1 Above 1 Ahead but expensive. Overtime or extra resources may be buying speed
Above 1 Below 1 Cheap but late. Work may be waiting on approvals or inputs
Above 1 Above 1 Ahead and under budget. Check the baseline, since padded estimates do this too

The S-curve: where PV, EV and AC sit

Cumulative PV forms an S: slow start, fast middle, slow finish.

S-curve for example 1: planned value, earned value and actual cost at month 4

A $200,000 project planned over 10 months. The gap between the blue and green lines is the schedule variance. The gap between green and red is the cost variance.

0k50k100k150k200k250k012345678910MonthBAC 200,000EAC 250,000PV 80,000AC 75,000EV 60,000

Illustrative example, not real project data. Month-4 values are PV $80,000, EV $60,000, AC $75,000. The dashed red line is the forecast under EAC = BAC / CPI.

Four worked examples of earned value formulas PMP style

Example 1: negative variance on both counts

A $200,000 migration is planned over 10 months. At month 4 the plan says 40% should be done, so PV is $80,000. The team reports 30% done, so EV is $60,000. The books show $75,000 spent.

  • CV = $60,000 – $75,000 = -$15,000. Over budget.
  • SV = $60,000 – $80,000 = -$20,000. Behind plan.
  • CPI = $60,000 / $75,000 = 0.80. Eighty cents of value per dollar spent.
  • SPI = $60,000 / $80,000 = 0.75. Three quarters of the planned pace.

Forecast: EAC = $200,000 / 0.80 = $250,000. ETC = $250,000 – $75,000 = $175,000. VAC = $200,000 – $250,000 = -$50,000. The overrun shows at month 4, not month 10.

Example 2: a healthy project

A $120,000 project is 50% planned and 55% done, with $55,000 spent. PV is $60,000 and EV is $66,000, so CV = $11,000, SV = $6,000, CPI = 1.20 and SPI = 1.10. EAC = $120,000 / 1.20 = $100,000, so VAC = $20,000. TCPI to BAC is 0.83: the team can run less efficiently and still finish on budget.

Example 3: a stalled project

A $90,000 project goes quiet. At month 3, PV is $30,000, EV is $18,000 and AC is $24,000. At month 6, PV is $60,000, EV is still $18,000 and AC is $36,000. People kept charging time, but no new work was finished.

Month CV SV CPI SPI
3 -$6,000 -$12,000 0.75 0.60
6 -$18,000 -$42,000 0.50 0.30

EV did not move between the two dates, so both indices fell. At month 6, EAC = $90,000 / 0.50 = $180,000, VAC = -$90,000, and TCPI to BAC = 1.33. A flat EV line with a rising AC line marks a stall. Then find the blocker, as our PMP situational questions guide explains.

Example 4: choosing the forecast

Back to example 1. The earned value formulas PMP prep lists for EAC give four answers, and the question tells you which one to use.

Variant Formula Use it when the question says Example 1
1. Typical variance BAC / CPI Current cost performance will continue $250,000
2. Atypical variance AC + (BAC – EV) The variance was a one-off, and remaining work follows the original budget $215,000
3. Cost and schedule both matter AC + (BAC – EV) / (CPI x SPI) Schedule pressure will also drive cost, for example crashing or overtime $308,333
4. New estimate AC + bottom-up ETC The original estimates are no longer valid, so remaining work is re-estimated $235,000

Variant 4 assumes the team re-estimates the remaining work at $160,000. Illustrative example.

Four forecasts for the same project (example 1)

Final cost forecast under each EAC variant. The budget is $200,000.

3. CPI x SPI$308,333
1. BAC / CPI$250,000
4. Bottom-up ETC$235,000
2. Atypical variance$215,000

Illustrative example. Every variant is over the $200,000 budget because the $15,000 already lost does not come back.

Variant 2 treats the $15,000 overrun as a one-time loss, such as a vendor penalty or one failed deployment. A weak estimate or a slow team points to variant 1.

TCPI: a target, not a forecast

TCPI divides the work left by the money left. It has two denominators, and the question decides which. Use BAC – AC when the original budget is the target. Use EAC – AC when management has approved a revised budget.

In example 1, TCPI to BAC is ($200,000 – $60,000) / ($200,000 – $75,000) = $140,000 / $125,000 = 1.12. The team has run at 0.80, so it must now be 40% more efficient than so far to land on budget. Few teams do that, so the practical answer is a change request or a re-baseline.

A check that catches errors. If EAC is BAC / CPI, then TCPI to EAC equals today’s CPI. Example 1 gives 0.80 for both. So it adds nothing when EAC assumes current performance continues. It helps when the revised EAC came from another source, such as a bottom-up estimate.

A memory aid for earned value formulas PMP questions use

  • EV always comes first. Every variance subtracts something from EV, and every index puts EV on top. You only choose the second term.
  • Cost pairs with actual cost, schedule pairs with planned value. CV and CPI use AC. SV and SPI use PV.
  • Below zero or below one is bad for all four of CV, SV, CPI and SPI.
  • Every EAC is spent plus still to spend. BAC / CPI looks different but equals AC + (BAC – EV) / CPI. The variants change only the second half.
  • TCPI is work left over money left. The work left is always BAC – EV. The money left is BAC – AC or EAC – AC.

Exam traps and how to avoid them

Most lost marks on earned value formulas PMP questions test come from five habits.

Trap How it catches people What to do
Swapping AC and EV A question gives percent complete and money spent. Percent complete gives EV, not AC Label every number PV, EV, AC or BAC before you calculate
Flipping the sign AC – EV looks natural, but cost variance is EV – AC. A negative result means over budget Remember EV first, then check the sign against the story
Using the wrong EAC All four look plausible. The wording decides Underline the phrase: continues, one-time, schedule also, new estimate
Wrong TCPI denominator BAC – AC and EAC – AC differ when the budget has been revised Ask which budget the sponsor is holding you to
Trusting SPI at the end Once the planned finish date passes, PV equals BAC and SPI drifts toward 1 even when late Judge a late project by the finish date and the remaining work, not by SPI alone

A $100,000 project plans to finish at month 10, so PV equals $100,000 from then on. At month 10 with $90,000 earned, SPI = 0.90 and SV = -$10,000. If the work finishes at month 12, SPI = 1.00 and SV = $0, although the project is two months late.

Forecasts should include reserves, which our PMP risk management guide covers.

Six illustrative practice questions

These practice questions on the earned value formulas PMP candidates study are our own illustrative questions, not PMI exam questions. Cover the answer, calculate, then check.

Question 1

PV is $50,000, EV is $40,000 and AC is $45,000. What are CPI and SPI, and what do they mean?

Answer: CPI = 40,000 / 45,000 = 0.89. SPI = 40,000 / 50,000 = 0.80. Both are below 1, so the project is over budget and behind schedule. CV = -$5,000 and SV = -$10,000.

Question 2

BAC is $300,000 and CPI is 0.75. The sponsor expects current cost performance to continue. What are EAC and VAC?

Answer: EAC = 300,000 / 0.75 = $400,000. VAC = 300,000 – 400,000 = -$100,000. The project is forecast to overrun by $100,000.

Question 3

BAC is $500,000, EV is $200,000 and AC is $250,000. A flood caused a one-time $50,000 loss, and the remaining work will run at the planned rate. What are EAC and ETC?

Answer: The loss is atypical, so EAC = 250,000 + 300,000 = $550,000. ETC = EAC – AC = $300,000.

Question 4

BAC is $400,000, EV is $150,000 and AC is $200,000. The sponsor will not raise the budget. What is the TCPI, and what should the project manager conclude?

Answer: TCPI = (400,000 – 150,000) / (400,000 – 200,000) = 1.25. The team has delivered a CPI of 0.75, so it would need to be far more efficient. The manager should take the gap to the sponsor with options: reduce scope, add funding or re-baseline.

Question 5

An $80,000 project should be 50% complete but is 40% complete, with $36,000 spent. What are SV and CV?

Answer: PV = $40,000, EV = $32,000. SV = 32,000 – 40,000 = -$8,000. CV = 32,000 – 36,000 = -$4,000. Percent figures give PV and EV, and the spend gives AC.

Question 6

BAC is $100,000, PV is $50,000, EV is $40,000 and AC is $50,000. Deadline pressure means both cost and schedule performance will affect the rest of the work. What is EAC?

Answer: CPI = 0.80 and SPI = 0.80, so CPI x SPI = 0.64. EAC = 50,000 + (100,000 – 40,000) / 0.64 = $143,750.

Where this fits in your study plan

Two sessions cover the earned value formulas PMP candidates need: one for definitions and signs, one for forecasting and TCPI. Place them in the finance and status weeks of our 8-week PMP study plan, then retry the six questions a week later. AgileFever lists a PMP course on its PMP training page. Check PMI’s training partner directory before you enrol in any live class, because PMI’s rules for live classes change on December 1, 2026.

Questions people ask

Is earned value on the PMP exam?

PMI’s July 2026 Exam Content Outline does not use the words earned value or EVM, and it lists no formulas. It does ask candidates to monitor financial variations, analyze schedule variation and measure project metrics, which is what these formulas do. Learn them, but expect no fixed number of calculation questions.

What are the earned value formulas PMP candidates must memorize?

CV = EV – AC, SV = EV – PV, CPI = EV / AC, SPI = EV / PV, EAC = BAC / CPI in the typical case, ETC = EAC – AC, VAC = BAC – EAC, and TCPI = (BAC – EV) / (BAC – AC) for the original budget. Three more EAC variants cover one-off variances, cost with schedule, and bottom-up estimates.

Which EAC formula should I use?

Match the wording. Current performance continues: BAC / CPI. One-time variance: AC + (BAC – EV). Cost and schedule both drive the rest: AC + (BAC – EV) / (CPI x SPI). New estimate for remaining work: add it to AC.

What does a TCPI above 1 mean?

It means each remaining dollar must earn more than a dollar of value to hit the target. A TCPI of 1.12 asks for $1.12 of work per dollar left. A large gap against your current CPI, such as 1.12 against 0.80, signals a target that needs a change request.

What is the difference between EAC, ETC and VAC?

EAC is the forecast total cost of the project. ETC is the part still to spend, EAC – AC. VAC is the forecast gap against the original budget, BAC – EAC. A negative VAC means a forecast overrun, and a positive VAC means a forecast saving.

Contact Us

    By checking the box, you consent to receive registrations, class reminders, updates, support text messages from AgileFever at the provided number. Message and data rates may apply. Message frequency varies (typically 1–2 msgs/week). To end messaging from us, you may always reply with STOP. You may also reply with HELP for more information. Check Privacy Policy and Terms & Conditions.