Written by the AgileFever editorial team. Facts checked on November 25, 2026 against the official pages of the organizations named in this post. AgileFever sells training for some of the topics covered here, and we say so wherever it applies. Definitions come from PMI’s scheduling publications. Every network and question below is our own invented teaching example, computed and cross-checked by script.
Critical path method PMP questions reward practice with numbers: merges, float, lead and lag, changed durations and crashing. Below: five invented networks, PMI’s terms, common traps and five practice questions, alongside our guides on the exam format and situational questions.
Critical path method PMP: what the exam outline says
PMI’s July 2026 outline puts scheduling in the Process domain (41% of the exam), Task 8, “Plan and manage schedule”. The enablers include creating and baselining a schedule and analyzing schedule variation. The outline does not name the critical path method, float or crashing, so treat them as the techniques behind those enablers, not as a published list of tested formulas. Read the wording in PMI’s July 2026 Exam Content Outline, checked November 25, 2026.
About 40% of items are predictive and 60% are agile or hybrid, per the same outline. Critical path work sits in the predictive share. Our agile and hybrid guide covers the rest. Expect four question shapes: find the path or duration, find a float, say what a change does, and choose how to shorten the schedule. The examples follow that order.
The formulas, with PMI’s terms
PMI’s Practice Standard for Scheduling and its 2006 Global Congress paper on CPM calculations define these terms. We paraphrase them. Both use activity-on-node diagrams: each box is an activity, arrows show order.
| Term | Meaning | Calculation |
|---|---|---|
| Early start (ES) | Earliest the activity can begin | Largest EF among predecessors, plus lag, minus lead. First activity: 0 |
| Early finish (EF) | Earliest it can end | ES + duration |
| Late finish (LF) | Latest it can end without delaying the project | Smallest LS among successors. Last activity: its own EF |
| Late start (LS) | Latest it can begin | LF – duration |
| Total float, or slack | Slip allowed before the project end moves | LS – ES, or LF – EF |
| Free float | Slip allowed before any successor’s early start moves | Smallest successor ES – EF, less any lag |
| Critical path | Longest path, sets the duration | Activities with zero total float. There can be several |
| Lag and lead | A wait, and an overlap | Lag adds time to the successor’s start. Lead is a negative lag |
Two counting styles exist. PMI’s paper starts the first activity at day zero (EF = ES + duration). Some questions count the first day as day 1 (EF = ES + duration – 1). Float and project length are identical either way. Follow the question’s start number.
The method in six steps
Add the durations along every route. This answers many questions before any pass.
Left to right. EF = ES + duration. At a merge, take the largest EF.
The largest EF at the end of the network.
Right to left. Last LF = project duration, LS = LF – duration. At a split, take the smallest LS.
Total float = LS – ES, checked with LF – EF. Free float = smallest successor ES – EF.
Join the zero-float activities. Their durations must add up to the project duration.
PMI’s paper gives three checks. Free float never exceeds total float. The critical path runs unbroken from start to finish. Nothing comes out negative. Every example below passes them.
Example 1: forward pass, backward pass and the critical path
Illustrative example: a release plan. A requirements (3 days) leads to B design (4) and C hardware order (2). D build (5) follows B. E install (3) follows C. F test (2) follows D and E.
Top corners: early start and finish. Bottom corners: late start and finish. Middle: total float. Red: critical.
Forward pass: B runs 3 to 7 and D runs 7 to 12. C runs 3 to 5 and E runs 5 to 8. F needs both D and E, so it starts at the larger finish, 12, and ends at 14. Backward pass: F must start by 12. E must end by 12, so it starts by 9. A has two successors, B (late start 3) and C (late start 7), and takes the smaller, 3.
| Activity | Total float | Free float | Critical? |
|---|---|---|---|
| A | 0 | 0 | Yes |
| B | 0 | 0 | Yes |
| C | 4 | 0 | No |
| D | 0 | 0 | Yes |
| E | 4 | 4 | No |
| F | 0 | 0 | Yes |
A-B-D-F adds to 14 days with no float. A-C-E-F adds to 10, so C and E carry 4 days of total float.
Example 2: total float and free float differ
“Without delaying its successor” asks for free float. “Without delaying the project” asks for total float. Illustrative example: A (3 days) leads to B (5), C (2) and D (4). B and C feed E (6). D feeds F (3). E and F feed G (2).
| Activity | Total float | Free float | Critical? |
|---|---|---|---|
| A | 0 | 0 | Yes |
| B | 0 | 0 | Yes |
| C | 3 | 3 | No |
| D | 4 | 0 | No |
| E | 0 | 0 | Yes |
| F | 4 | 4 | No |
| G | 0 | 0 | Yes |
D has 4 days of total float but 0 of free float: it ends at 7 and its successor F starts at 7. If D slips 3 days, F starts at 10, the project still ends on day 16, and F’s float falls from 4 to 1. A 5-day slip passes D’s float by one day and the project ends on day 17.
Example 3: lead and lag
A lag adds waiting time to a link. A lead lets the successor start before the predecessor ends. PMI’s standard gives a ten-day lead as starting ten days early. Illustrative example: A (5 days) leads to B (4) and C (6), and both feed D (3). Three versions of the plan:
| Version | Link changes | A-B-D | A-C-D | Project | Critical |
|---|---|---|---|---|---|
| a | None | 12 | 14 | 14 | A-C-D |
| b | 2-day lag, A to B (an approval wait) | 14 | 14 | 14 | Both |
| c | b plus a 2-day lead, B to D | 12 | 14 | 14 | A-C-D |
In version c, the lag pushes B to start at 7 and finish at 11. D could start 2 days before that, at 9, but C finishes at 11, so D starts at 11. The lead gained nothing because C controls D, and B has 2 days of float. A lag lengthens a path, a lead shortens it, and a lead on a non-critical path never shortens the project.
Example 4: durations change
Schedule-variation items in critical path method PMP practice give a changed duration and ask for the new length or critical path. Return to the path sums. Here are six changes to the example 1 network.
Computed by forward pass. Illustrative example.
Shortening a critical activity helps only until another path ties, which is why cutting D by 4 days saves 4 and not 5. Shortening a non-critical activity saves nothing. Delaying a non-critical activity costs nothing until it uses its float, and then the critical path moves.
Example 5: crashing and fast tracking
PMI’s scheduling standard names both as schedule compression. Crashing adds resources or cost to critical activities, typically raising cost. Fast tracking overlaps planned-in-sequence work and raises the risk of rework. Crashing works only on effort-driven activities.
Illustrative example on the example 1 network. Cost per day and maximum days: A $400 and 1, B $300 and 1, C $200 and 1, D $500 and 2, E $250 and 1. F cannot be crashed. Crash the cheapest critical activity, then recalculate.
| Target | Cheapest plan | Extra cost |
|---|---|---|
| 13 days | B by 1 | $300 |
| 12 days | A and B by 1 each | $700 |
| 11 days | A and B by 1, D by 1 | $1,200 |
| 10 days | A and B by 1, D by 2 | $1,700 |
We tried every combination of crash days to confirm these are the cheapest plans. After the 12-day plan, A-C-E-F takes 9 days. Crashing C, the cheapest activity at $200, would leave the project at 14 days, because C is not critical.
Fast tracking option: start D one day before B finishes, a 1-day lead. The project becomes 13 days with no crash cost, but the rework risk rises because D starts on unfinished design. Crash far enough and a second path ties: cutting D to 1 day makes all six activities critical.
Traps that cost marks
- Taking the smaller EF at a merge. Forward takes the larger, backward takes the smaller.
- Starting the backward pass at zero. Start at the last activity, with LF equal to its EF.
- Mixing day-zero and day-1 counts in one problem.
- Giving total float when the question asks for free float. Read “successor” and “project”.
- Adding every duration. Only the longest path counts.
- Crashing a cheap but non-critical activity.
- Treating a lag as a lead. A lag adds time, a lead removes it.
- Assuming one critical path and one owner per float. Paths can tie and float on a chain is shared.
Practice set: five illustrative questions
These critical path method PMP practice questions are our own invention, not PMI items, and they do not predict the exam. Questions 1, 2, 4 and 5 use one network: A (4 days) leads to B (6) and C (3). B leads to D (5). C leads to E (7). D and E lead to F (2).
Question 1
What are the duration and critical path? A) 16 days, A-C-E-F. B) 17 days, A-B-D-F. C) 17 days, all six activities. D) 27 days.
Answer: B. A-B-D-F is 4 + 6 + 5 + 2 = 17. A-C-E-F is 16. Options C and D add parallel work.
Question 2
What is the total float of E? A) 0. B) 1 day. C) 3 days. D) 7 days.
Answer: B. E starts at 7 and ends at 14. F cannot start before D ends at 15, so E’s late start is 8. 8 – 7 = 1.
Question 3
A second network: S (2 days) leads to T (5), U (3) and W (4). T and U lead to V (6). W leads to X (2). V and X lead to Y (3). What are W’s total and free float? A) 0 and 0. B) 5 and 0. C) 5 and 5. D) 0 and 5.
Answer: B. The critical path S-T-V-Y takes 16 days. W ends at 6 and its only successor X starts at 6, so free float is 0. W’s late start is 7 against an early start of 2, so total float is 5.
Question 4
A 3-day approval wait is added between A and C as a lag. What happens? A) Nothing. B) 19 days and the critical path becomes A-C-E-F. C) 20 days. D) 17 days with more float on C.
Answer: B. A-C-E-F becomes 4 + 3 + 3 + 7 + 2 = 19, longer than A-B-D-F at 17.
Question 5
You must save one day. F cannot be crashed. Cost per day: A $900, B $500, C $200, D $700, E $300. What do you do? A) Crash C. B) Crash E. C) Crash B. D) Crash A.
Answer: C. Only critical activities (A, B, D) shorten the project, and B is cheapest. C and E sit on a 16-day path, so crashing them leaves 17 days. After B’s crash both paths take 16 days.
Where to go next
Practise until a full critical path method PMP pass takes under two minutes by hand. Decide how much time to give it with the 8-week plan or the 4-week plan. Still deciding whether to sit the exam? Read is PMP still worth it. AgileFever lists a course on its PMP training page. PMI sets its own rules for the 35 training hours, so check them with PMI before you pay any provider, including us.
Questions people ask
What is the critical path in PMP?
It is the longest path through the schedule network, and its length is the shortest time the project can finish. Activities on it have zero total float, so a delay to any of them delays the end date. A network can have more than one critical path.
What is the difference between total float and free float?
Total float is how long an activity can slip without delaying the project end date. Free float is how long it can slip without delaying a successor’s early start. Free float never exceeds total float, and it can be zero when total float is not.
How do you calculate float on the PMP exam?
Run a forward pass for early dates and a backward pass for late dates. Total float is late start minus early start, which equals late finish minus early finish. Free float is the smallest successor early start minus the activity’s early finish.
Does a lead or lag change the critical path method PMP answer?
It can. A lag adds time to a path and a lead removes it. In example 3 a 2-day lag made two paths tie, while a lead on the non-critical path left the project at 14 days. Recalculate every path total after adding either one, because the longest path may have changed.
What is the difference between crashing and fast tracking?
For critical path method PMP questions, remember crashing shortens critical activities by adding resources, so it costs money. Fast tracking overlaps activities planned in sequence, so it saves time at the price of rework risk. Apply either to the critical path only.
Is the critical path method PMP content tested directly?
PMI’s July 2026 outline lists schedule tasks such as creating a schedule and analyzing schedule variation. It does not name the critical path method, and PMI publishes no list of tested formulas. Learn the method well enough for calculation and scenario questions.