critical path method pmp

Critical Path Method Worked Examples for the PMP Exam

Table of Contents

Short answer. In critical path method PMP questions, the critical path is the longest path through the schedule network, and its length is the shortest time the project can finish. Find it with a forward pass (take the largest early finish of the predecessors), a backward pass (take the smallest late start of the successors), then total float = LS – ES and free float = smallest successor ES – EF. Zero total float means critical. In our first example the two paths run 14 and 10 days, so the project takes 14 days and the other path floats 4. The PMP exam has 180 questions in 240 minutes, per PMI. Checked on November 25, 2026.

Written by the AgileFever editorial team. Facts checked on November 25, 2026 against the official pages of the organizations named in this post. AgileFever sells training for some of the topics covered here, and we say so wherever it applies. Definitions come from PMI’s scheduling publications. Every network and question below is our own invented teaching example, computed and cross-checked by script.

Critical path method PMP questions reward practice with numbers: merges, float, lead and lag, changed durations and crashing. Below: five invented networks, PMI’s terms, common traps and five practice questions, alongside our guides on the exam format and situational questions.

Critical path method PMP: what the exam outline says

PMI’s July 2026 outline puts scheduling in the Process domain (41% of the exam), Task 8, “Plan and manage schedule”. The enablers include creating and baselining a schedule and analyzing schedule variation. The outline does not name the critical path method, float or crashing, so treat them as the techniques behind those enablers, not as a published list of tested formulas. Read the wording in PMI’s July 2026 Exam Content Outline, checked November 25, 2026.

About 40% of items are predictive and 60% are agile or hybrid, per the same outline. Critical path work sits in the predictive share. Our agile and hybrid guide covers the rest. Expect four question shapes: find the path or duration, find a float, say what a change does, and choose how to shorten the schedule. The examples follow that order.

The formulas, with PMI’s terms

PMI’s Practice Standard for Scheduling and its 2006 Global Congress paper on CPM calculations define these terms. We paraphrase them. Both use activity-on-node diagrams: each box is an activity, arrows show order.

Term Meaning Calculation
Early start (ES) Earliest the activity can begin Largest EF among predecessors, plus lag, minus lead. First activity: 0
Early finish (EF) Earliest it can end ES + duration
Late finish (LF) Latest it can end without delaying the project Smallest LS among successors. Last activity: its own EF
Late start (LS) Latest it can begin LF – duration
Total float, or slack Slip allowed before the project end moves LS – ES, or LF – EF
Free float Slip allowed before any successor’s early start moves Smallest successor ES – EF, less any lag
Critical path Longest path, sets the duration Activities with zero total float. There can be several
Lag and lead A wait, and an overlap Lag adds time to the successor’s start. Lead is a negative lag

Two counting styles exist. PMI’s paper starts the first activity at day zero (EF = ES + duration). Some questions count the first day as day 1 (EF = ES + duration – 1). Float and project length are identical either way. Follow the question’s start number.

The method in six steps

How to solve a schedule network question
1
List the paths
Add the durations along every route. This answers many questions before any pass.
2
Forward pass
Left to right. EF = ES + duration. At a merge, take the largest EF.
3
Project duration
The largest EF at the end of the network.
4
Backward pass
Right to left. Last LF = project duration, LS = LF – duration. At a split, take the smallest LS.
5
Float
Total float = LS – ES, checked with LF – EF. Free float = smallest successor ES – EF.
6
Critical path
Join the zero-float activities. Their durations must add up to the project duration.

PMI’s paper gives three checks. Free float never exceeds total float. The critical path runs unbroken from start to finish. Nothing comes out negative. Every example below passes them.

Example 1: forward pass, backward pass and the critical path

Illustrative example: a release plan. A requirements (3 days) leads to B design (4) and C hardware order (2). D build (5) follows B. E install (3) follows C. F test (2) follows D and E.

Example 1: every date and float

Top corners: early start and finish. Bottom corners: late start and finish. Middle: total float. Red: critical.

03A (3)0float 0337B (4)3float 0735C (2)7float 49712D (5)7float 01258E (3)9float 4121214F (2)12float 014

Forward pass: B runs 3 to 7 and D runs 7 to 12. C runs 3 to 5 and E runs 5 to 8. F needs both D and E, so it starts at the larger finish, 12, and ends at 14. Backward pass: F must start by 12. E must end by 12, so it starts by 9. A has two successors, B (late start 3) and C (late start 7), and takes the smaller, 3.

Activity Total float Free float Critical?
A 0 0 Yes
B 0 0 Yes
C 4 0 No
D 0 0 Yes
E 4 4 No
F 0 0 Yes

A-B-D-F adds to 14 days with no float. A-C-E-F adds to 10, so C and E carry 4 days of total float.

Example 2: total float and free float differ

“Without delaying its successor” asks for free float. “Without delaying the project” asks for total float. Illustrative example: A (3 days) leads to B (5), C (2) and D (4). B and C feed E (6). D feeds F (3). E and F feed G (2).

Example 2: float differs by activity
03A (3)0float 0338B (5)3float 0835C (2)6float 3837D (4)7float 411814E (6)8float 014710F (3)11float 4141416G (2)14float 016
Activity Total float Free float Critical?
A 0 0 Yes
B 0 0 Yes
C 3 3 No
D 4 0 No
E 0 0 Yes
F 4 4 No
G 0 0 Yes

D has 4 days of total float but 0 of free float: it ends at 7 and its successor F starts at 7. If D slips 3 days, F starts at 10, the project still ends on day 16, and F’s float falls from 4 to 1. A 5-day slip passes D’s float by one day and the project ends on day 17.

Float is shared along a chain. In example 1, C has total float 4 and free float 0. E has total float 4 and free float 4. They share the same 4 days. If C slips 3 days, E’s total float drops from 4 to 1 and the project date holds at 14.

Example 3: lead and lag

A lag adds waiting time to a link. A lead lets the successor start before the predecessor ends. PMI’s standard gives a ten-day lead as starting ten days early. Illustrative example: A (5 days) leads to B (4) and C (6), and both feed D (3). Three versions of the plan:

Version Link changes A-B-D A-C-D Project Critical
a None 12 14 14 A-C-D
b 2-day lag, A to B (an approval wait) 14 14 14 Both
c b plus a 2-day lead, B to D 12 14 14 A-C-D
Example 3, version c: a lag and a lead
lag 2lead 205A (5)0float 05711B (4)9float 213511C (6)5float 0111114D (3)11float 014

In version c, the lag pushes B to start at 7 and finish at 11. D could start 2 days before that, at 9, but C finishes at 11, so D starts at 11. The lead gained nothing because C controls D, and B has 2 days of float. A lag lengthens a path, a lead shortens it, and a lead on a non-critical path never shortens the project.

Example 4: durations change

Schedule-variation items in critical path method PMP practice give a changed duration and ask for the new length or critical path. Return to the path sums. Here are six changes to the example 1 network.

Project duration after each change to the example 1 network

Computed by forward pass. Illustrative example.

Base plan14 days
Shorten D by 2 days (5 to 3)12 days
Shorten D by 4 days (5 to 1)10 days, two critical paths
Shorten C by 1 day (2 to 1), a non-critical activity14 days
C slips by 4 days (2 to 6)14 days, two critical paths
C slips by 5 days (2 to 7)15 days, path moves

Shortening a critical activity helps only until another path ties, which is why cutting D by 4 days saves 4 and not 5. Shortening a non-critical activity saves nothing. Delaying a non-critical activity costs nothing until it uses its float, and then the critical path moves.

Example 5: crashing and fast tracking

PMI’s scheduling standard names both as schedule compression. Crashing adds resources or cost to critical activities, typically raising cost. Fast tracking overlaps planned-in-sequence work and raises the risk of rework. Crashing works only on effort-driven activities.

Illustrative example on the example 1 network. Cost per day and maximum days: A $400 and 1, B $300 and 1, C $200 and 1, D $500 and 2, E $250 and 1. F cannot be crashed. Crash the cheapest critical activity, then recalculate.

Target Cheapest plan Extra cost
13 days B by 1 $300
12 days A and B by 1 each $700
11 days A and B by 1, D by 1 $1,200
10 days A and B by 1, D by 2 $1,700
Example 5: after crashing A and B by one day each
02A (2)0float 0225B (3)2float 0524C (2)5float 37510D (5)5float 01047E (3)7float 3101012F (2)10float 012

We tried every combination of crash days to confirm these are the cheapest plans. After the 12-day plan, A-C-E-F takes 9 days. Crashing C, the cheapest activity at $200, would leave the project at 14 days, because C is not critical.

Fast tracking option: start D one day before B finishes, a 1-day lead. The project becomes 13 days with no crash cost, but the rework risk rises because D starts on unfinished design. Crash far enough and a second path ties: cutting D to 1 day makes all six activities critical.

Traps that cost marks

  • Taking the smaller EF at a merge. Forward takes the larger, backward takes the smaller.
  • Starting the backward pass at zero. Start at the last activity, with LF equal to its EF.
  • Mixing day-zero and day-1 counts in one problem.
  • Giving total float when the question asks for free float. Read “successor” and “project”.
  • Adding every duration. Only the longest path counts.
  • Crashing a cheap but non-critical activity.
  • Treating a lag as a lead. A lag adds time, a lead removes it.
  • Assuming one critical path and one owner per float. Paths can tie and float on a chain is shared.

Practice set: five illustrative questions

These critical path method PMP practice questions are our own invention, not PMI items, and they do not predict the exam. Questions 1, 2, 4 and 5 use one network: A (4 days) leads to B (6) and C (3). B leads to D (5). C leads to E (7). D and E lead to F (2).

Question 1

What are the duration and critical path? A) 16 days, A-C-E-F. B) 17 days, A-B-D-F. C) 17 days, all six activities. D) 27 days.

Answer: B. A-B-D-F is 4 + 6 + 5 + 2 = 17. A-C-E-F is 16. Options C and D add parallel work.

Question 2

What is the total float of E? A) 0. B) 1 day. C) 3 days. D) 7 days.

Answer: B. E starts at 7 and ends at 14. F cannot start before D ends at 15, so E’s late start is 8. 8 – 7 = 1.

Question 3

A second network: S (2 days) leads to T (5), U (3) and W (4). T and U lead to V (6). W leads to X (2). V and X lead to Y (3). What are W’s total and free float? A) 0 and 0. B) 5 and 0. C) 5 and 5. D) 0 and 5.

Answer: B. The critical path S-T-V-Y takes 16 days. W ends at 6 and its only successor X starts at 6, so free float is 0. W’s late start is 7 against an early start of 2, so total float is 5.

Question 4

A 3-day approval wait is added between A and C as a lag. What happens? A) Nothing. B) 19 days and the critical path becomes A-C-E-F. C) 20 days. D) 17 days with more float on C.

Answer: B. A-C-E-F becomes 4 + 3 + 3 + 7 + 2 = 19, longer than A-B-D-F at 17.

Question 5

You must save one day. F cannot be crashed. Cost per day: A $900, B $500, C $200, D $700, E $300. What do you do? A) Crash C. B) Crash E. C) Crash B. D) Crash A.

Answer: C. Only critical activities (A, B, D) shorten the project, and B is cheapest. C and E sit on a 16-day path, so crashing them leaves 17 days. After B’s crash both paths take 16 days.

Where to go next

Practise until a full critical path method PMP pass takes under two minutes by hand. Decide how much time to give it with the 8-week plan or the 4-week plan. Still deciding whether to sit the exam? Read is PMP still worth it. AgileFever lists a course on its PMP training page. PMI sets its own rules for the 35 training hours, so check them with PMI before you pay any provider, including us.

Questions people ask

What is the critical path in PMP?

It is the longest path through the schedule network, and its length is the shortest time the project can finish. Activities on it have zero total float, so a delay to any of them delays the end date. A network can have more than one critical path.

What is the difference between total float and free float?

Total float is how long an activity can slip without delaying the project end date. Free float is how long it can slip without delaying a successor’s early start. Free float never exceeds total float, and it can be zero when total float is not.

How do you calculate float on the PMP exam?

Run a forward pass for early dates and a backward pass for late dates. Total float is late start minus early start, which equals late finish minus early finish. Free float is the smallest successor early start minus the activity’s early finish.

Does a lead or lag change the critical path method PMP answer?

It can. A lag adds time to a path and a lead removes it. In example 3 a 2-day lag made two paths tie, while a lead on the non-critical path left the project at 14 days. Recalculate every path total after adding either one, because the longest path may have changed.

What is the difference between crashing and fast tracking?

For critical path method PMP questions, remember crashing shortens critical activities by adding resources, so it costs money. Fast tracking overlaps activities planned in sequence, so it saves time at the price of rework risk. Apply either to the critical path only.

Is the critical path method PMP content tested directly?

PMI’s July 2026 outline lists schedule tasks such as creating a schedule and analyzing schedule variation. It does not name the critical path method, and PMI publishes no list of tested formulas. Learn the method well enough for calculation and scenario questions.

Contact Us

    By checking the box, you consent to receive registrations, class reminders, updates, support text messages from AgileFever at the provided number. Message and data rates may apply. Message frequency varies (typically 1–2 msgs/week). To end messaging from us, you may always reply with STOP. You may also reply with HELP for more information. Check Privacy Policy and Terms & Conditions.