Written by the AgileFever editorial team. Facts checked on November 25, 2026 against the official pages of the organizations named in this post. AgileFever sells training for some of the topics covered here, and we say so wherever it applies. The sequence of the agenda comes from Scaled Agile’s PI Planning Facilitator’s Guide. The clock times, checklists and templates are AgileFever’s own working versions.
This PI planning agenda gives you the order Scaled Agile publishes, then turns it into start and end times you can paste into a calendar, with role and readiness checklists, three templates and a US and India timetable. For what PI Planning is and why it exists, read our older guide to SAFe PI Planning. This post is for the person who has to run the two days.
The PI planning agenda Scaled Agile publishes
Scaled Agile’s framework page describes PI Planning as typically a 2-day event for the whole Agile Release Train (ART), every 8 to 12 weeks, led by the RTE, and held in the Innovation and Planning Iteration so planning does not eat delivery time. Page updated March 15, 2026. The step order below comes from Scaled Agile’s PI Planning Facilitator’s Guide, also read November 25, 2026.
| Block | Step | What the guide says happens |
|---|---|---|
| Day 1 morning | Opening, business context, product and solution vision, architecture vision, development practices, planning context | Briefings from a senior executive or Business Owner, Product Management and System Architects |
| Day 1 afternoon | Team breakouts, hourly coach syncs | The longest session. Teams estimate capacity, write and sequence stories, draft PI Objectives, list risks |
| Day 1 end | Draft plan review | Each team shows capacity and load, draft objectives and risks |
| Day 1 evening | Management review and problem-solving | Management settles scope and constraint problems |
| Day 2 morning | Planning adjustments, breakouts continue | Management announces decisions. Teams finalize SMART PI Objectives. Business Owners assign value |
| Day 2 late afternoon | Final plan review, ROAM, the commitment, retrospective, next steps | Business Owners approve plans. Risks go through ROAM. Everyone votes on confidence |
Source: Scaled Agile, SAFe PI Planning Facilitator’s Guide (PDF), read November 25, 2026.
Two rules from the same guide shape the timetable. A story larger than 8 points is split, for new ARTs. And if the confidence vote is below three fingers, the work is incomplete: scope and resources change and planning continues, because the guide values alignment and commitment over strict time box adherence.
A two-day PI planning agenda with start and end times
The timetable assumes 6 teams, a 09:00 start and one room (or one video call). Scaled Agile’s RTE tips recommend starting around 09:00 rather than 08:00 so people who commute by train or bus can arrive. The blocks add up: 555 minutes on Day 1, of which teams attend 495, and 480 on Day 2.
Day 1
| Time | Min | Block | Lead | What happens |
|---|---|---|---|---|
| 09:00 to 09:20 | 20 | Opening | RTE | Purpose, agenda, working agreements, logistics. |
| 09:20 to 10:05 | 45 | Business context | Business Owner or senior executive | Current state of the business and strategic themes. |
| 10:05 to 11:05 | 60 | Product and solution vision | Product Management | Vision, roadmap, feature priorities. |
| 11:05 to 11:20 | 15 | Break | ||
| 11:20 to 12:05 | 45 | Architecture vision | System Architect | Architecture vision, Enabler Epics, non-functional requirements. |
| 12:05 to 12:30 | 25 | Development practices | Technical leader | Changes to practices and the Continuous Delivery Pipeline. |
| 12:30 to 12:45 | 15 | Planning context | RTE | How the two days run. |
| 12:45 to 13:30 | 45 | Lunch | ||
| 13:30 to 16:00 | 150 | Team breakouts 1 | Each team with Product Management | Capacity, stories, estimates, draft PI Objectives, risks. Two 10-minute coach syncs. |
| 16:00 to 16:15 | 15 | Break | ||
| 16:15 to 17:15 | 60 | Draft plan review | Each team presents | Capacity, draft objectives, risks. 6 teams at 10 minutes each. |
| 17:15 to 18:15 | 60 | Management review and problem-solving | Management, Product Management, key stakeholders | Scope, constraints, any over-scoped team. Teams are free to leave. |
Day 2
| Time | Min | Block | Lead | What happens |
|---|---|---|---|---|
| 09:00 to 09:15 | 15 | Day 2 opening | RTE | Agenda and goals for the day. |
| 09:15 to 09:45 | 30 | Planning adjustments | Senior manager for the management team | Decisions from last night’s review, said as one voice. |
| 09:45 to 13:00 | 195 | Team breakouts 2 | Each team | Refine plans. Finalize SMART team PI Objectives. Business Owners assign business value. RTE updates the ART planning board. |
| 13:00 to 13:45 | 45 | Lunch | ||
| 13:45 to 15:15 | 90 | Final plan review | Each team presents | Final objectives with business value, load, risks. Business Owners approve. 6 teams at 15 minutes each. |
| 15:15 to 15:30 | 15 | Break | ||
| 15:30 to 16:15 | 45 | Program risks (ROAM) | RTE with the whole ART | Each risk is Resolved, Owned, Accepted or Mitigated. |
| 16:15 to 16:35 | 20 | Confidence vote | Teams, Business Owners, ART leadership | Five-finger vote. Below three fingers, planning continues. |
| 16:35 to 16:50 | 15 | Planning retrospective | RTE | What went well, what did not, what to change next time. |
| 16:50 to 17:00 | 10 | Next steps | RTE | Tooling, cadences, clean-up, thanks. |
Illustrative example for 6 teams. Scaled Agile publishes the order, not these times.
To fit your train, change two numbers. The draft plan review costs 10 minutes per team and the final plan review 15. Add a team and Day 1 grows by 10 minutes and Day 2 by 15. Take the minutes out of the matching breakout block, not out of the reviews.
Minutes by type of activity, from the timetable above.
Illustrative example from the timetable in this post, not measured data.
Breakouts take 33% of the time. That matches the guide, which calls team breakouts the longest and most critical session. Briefings past the 210 minutes shown before the first breakout cost planning time.
Role-by-role checklist for the PI planning agenda
| Role | Before | During | After |
|---|---|---|---|
| Release Train Engineer (RTE) | Finalize the agenda with timeboxes, venue and tools. Rehearse briefings. Send the agenda ahead | Facilitate every block. Keep the ART planning board current. Run ROAM and the vote | Aggregate team objectives into ART PI Objectives. Set cadences. Start next preparation |
| Product Management | Prioritize features in the ART Backlog. Prepare vision and roadmap | Present the vision. Answer scope questions in breakouts. Join the management review | Update the roadmap for the next PI |
| System Architect | Prepare the architecture vision, Enabler Epics, refactors and non-functional requirements | Present on Day 1. Visit teams that miss technical dependencies or Enablers | Keep Enabler work visible on the board |
| Business Owners | Agree priorities with each other before Day 1. Prepare the business context | Set context. Assign business value. Question and approve each final plan. Vote | Follow progress against the PI Objectives they valued |
| Scrum Masters and Team Coaches | Confirm team capacity, holidays and leave. Check the team backlog is refined | Facilitate the team breakout. Run the hourly coach sync of 5 to 10 minutes. Present the team’s plan | Load stories and objectives into the tracking tool |
Duties follow Scaled Agile’s Facilitator’s Guide. Before and After items beyond the guide, such as rehearsals and System Demo follow-up, are AgileFever’s recommendations.
Pre-PI planning readiness checklist
Scaled Agile groups preparation into three areas: organizational readiness, content readiness and logistics readiness. The checklist below is our working list for those three areas. Start it four weeks before the event. If your train has never run PI Planning, also read our SAFe readiness checklist.
| Area | Check | Owner | Done when |
|---|---|---|---|
| Organizational | The teams that plan together are named and each has a Scrum Master or coach and a Product Owner | RTE | A roster with every name and location exists |
| Organizational | Business Owners agree on priorities | Business Owners | One ranked list, no open disagreements |
| Content | Features in the ART Backlog are prioritized | Product Management | Ordered list with acceptance criteria for the top features |
| Content | Vision, roadmap, business context and architecture vision are ready and rehearsed | Product Management, Business Owner, System Architect | A dry run ran inside its timebox |
| Logistics | Venue or video platform is booked and tested | RTE | A test call with every site and every breakout room |
| Logistics | Planning tool or physical board is set up with iterations, teams and feature cards | RTE | Every feature card exists once |
| Logistics | Agenda with timeboxes is final and sent | RTE | Attendees have it 5 days ahead |
Areas come from Scaled Agile. The individual checks and the 5-day rule are AgileFever’s. An RTE writing for Scaled Agile advises against over-preparing stories, because that work is wasted when scope changes.
Templates: objectives, ROAM log and program board
Team PI Objectives
Each team writes SMART objectives and marks which are committed and which are uncommitted. Business Owners then assign business value, including to uncommitted objectives.
| Objective (SMART) | Committed or uncommitted | Features and stories | Business value (Business Owner) |
|---|---|---|---|
| Customers can reschedule a delivery slot in the mobile app, live for 10% of users by the end of iteration 4 | Committed | Feature 2, stories 2.1 to 2.6 | Set on Day 2 |
| Reduce checkout API timeouts so that errors stay under 1% of requests by iteration 3 | Committed | Enabler Feature 5 | Set on Day 2 |
Illustrative example. The objectives are invented to show the format.
ROAM risk log
Teams hand their risks to the RTE at the final plan review, and the ART sorts each into one category. Our reading of the four words: Resolved, the ART agrees it is no longer a problem; Owned, a named person works on it; Accepted, it cannot be avoided and the ART lives with it; Mitigated, a plan lowers its impact.
| Risk | Raised by | ROAM status | Owner | Next step and date |
|---|---|---|---|---|
| Payments sandbox is not ready before iteration 2 | Team B | Owned | Product Management | Confirm vendor date by end of day 2 |
| Two engineers on leave in iteration 3 | Team A | Accepted | Scrum Master | Plan load at 80% for that iteration |
| Shared test environment is booked by another ART | Team C | Mitigated | RTE | Reserve a window, move tests earlier |
Illustrative example. Names and risks are invented.
Program board
The ART planning board shows features by team and iteration, dependencies and milestones. Scaled Agile lists it as an output of PI Planning.
Illustrative example. Feature names, teams and dependencies are invented.
Running the PI planning agenda across US and India time zones
Scaled Agile says real-time virtual planning works when all ART members take part. Its Distributed PI Planning article lists six areas to settle: locations, agenda for multiple time zones, facilities, working agreements, tooling and facilitation. It advises keeping each team in one place, rotating Business Owners, Product Management and architects to remote sites, and handing out a roster with locations and time differences on Day 1. Its timetable section is for members on Scaled Agile’s site, so read it there before you commit.
A shared window is the practical problem. In February, New York is 10 hours 30 minutes behind India (the code behind this timetable checks that offset). A 08:30 start in New York is 19:00 in India. The illustrative plan below stretches the event to three days and plans only inside shared windows. Between windows, each region’s teams keep planning in their own business hours.
| Day | US Eastern | India (IST) | Minutes | Shared window holds |
|---|---|---|---|---|
| Day 1 | 08:30 to 12:30 | 19:00 to 23:00 | 240 | Briefings, then each team starts planning |
| Day 2 | 08:30 to 10:45 | 19:00 to 21:15 | 135 | Draft plans and management review |
| Day 3 | 08:30 to 13:00 | 19:00 to 23:30 | 270 | Final plans, risks, vote |
Illustrative example for Tuesday to Thursday, February 9 to 11, 2027, with 6 teams. Scaled Agile’s own multi-time-zone agenda is in its Distributed PI Planning article.
India finishes late on Day 3, at 23:30 IST. Swap which region takes the late window every PI. Plan 15-minute breaks every 60 to 75 minutes, as one Scaled Agile RTE recommends for remote events.
Common failures in a PI planning agenda and the fix
| What goes wrong | Why it happens | Fix |
|---|---|---|
| Teams are 50 to 100% over-scoped | Feature list was never matched to capacity | Management review cuts scope, revisits commitments or moves people. Do not move to the final commitment until the plan is realistic |
| Vote below three fingers | Risks are still open or scope is too large | Adjust scope and resources and keep planning. Alignment and commitment come before the timebox |
| Teams skip technical dependencies and Enablers | Architecture vision was too abstract | Prompt teams to write Enabler stories. Make the board show the dependencies. Send the System Architect to the team |
| Teams arrive with every story written | Over-preparation | Bring known features and capacity. Write stories in the room |
The first three rows follow the Overcoming Challenges table in Scaled Agile’s Facilitator’s Guide, read November 25, 2026.
Who runs this agenda, and how to train for it
The RTE facilitates the whole event. Our week in the life of an RTE shows where PI Planning sits in the RTE’s cycle, and release train training curriculum sets out which roles on the train learn what, and when. For the RTE credential itself, see SAFe RTE certification: prerequisites, cost and exam format.
AgileFever sells the Release Train Engineer (RTE) course. As listed on November 25, 2026, the price is $2,200 in the US and ₹125,000 in India before 18% GST, shown next to struck-through list prices of $2,995 and ₹199,999. Listed batches: Dec 4 to 6 and Dec 14 to 16, 2026; Jan 22 to 24 and Jan 25 to 27, Feb 19 to 21 and Feb 22 to 24, and Mar 26 to 28 and Mar 29 to 31, 2027. If you want a private class for your own train, how many people to put in a private SAFe class covers group size and scheduling.
Additional discounts are available. Contact us to know more.
Questions people ask
How long is a PI planning agenda?
Scaled Agile describes PI Planning as typically a 2-day event for the whole ART, held every 8 to 12 weeks. Our illustrative timetable runs 09:00 to 17:15 on Day 1 for teams, with a management review after, and 09:00 to 17:00 on Day 2.
What is on day 1 of a PI planning agenda?
Day 1 starts with an opening, business context, product and solution vision, architecture vision, development practices and planning context. The afternoon is team breakouts, a draft plan review and a management review and problem-solving meeting.
What happens on day 2 of PI Planning?
Management announces its planning adjustments. Teams finalize PI Objectives and Business Owners assign business value. Teams present final plans, the ART handles risks with ROAM, everyone votes on confidence, and the RTE runs a short retrospective.
What score passes the confidence vote?
Scaled Agile’s guide says a vote below three fingers means the work is incomplete. Scope and resources change and planning continues until the ART can commit.
Can PI Planning run remotely?
Yes. Scaled Agile says real-time virtual planning works when all ART members take part, and its Distributed PI Planning article covers locations, agenda, facilities, working agreements, tooling and facilitation.
Who runs the PI planning agenda?
The Release Train Engineer leads the event. Business Owners and Product Management present context and vision, System Architects present the architecture vision, and Scrum Masters and Team Coaches facilitate each team’s breakouts.