kanban forecasting

Probabilistic Forecasting for Kanban: Monte Carlo in Plain Language

Table of Contents

Short answer. Kanban forecasting means answering from your own finished work, not from estimates. Count the items your team finished each day, draw days from that list at random until the total reaches your backlog, repeat 10,000 times, and read the percentiles. In the illustrative history below (40 working days, 60 items, 1.5 items a day), 45 items take 30 working days at 50% confidence, 36 at 85% and 39 at 95%. The plain average says 30 days and is met in only 51% of runs. For the other question, how much by a date, the same history gives 17 items in 15 working days at 85% confidence.

Written by the AgileFever editorial team. Facts checked on November 25, 2026 against the official pages of the organizations named in this post. AgileFever sells training for some of the topics covered here, and we say so wherever it applies. Definitions come from the Kanban Guide, edition 2025.5, published May 2025. All numbers in the worked examples come from invented data, computed in Python with fixed random seeds and checked with assertions.

Kanban forecasting replaces the question “how big is each item?” with “what has this system actually delivered?” The Kanban Guide asks a team for a service level expectation, a forecast built from historical cycle time. A Monte Carlo run goes one step further and turns that same history into a range of dates for a whole backlog. This post builds both kinds of kanban forecasting by hand, then covers history length, percentiles and five data problems that break the result. A shorter weekly example already exists in our post on Kanban AI triage and forecasting, so this one uses daily data and goes deeper.

Kanban forecasting: four questions, four inputs

Teams go wrong when one method answers a different question. The metric definitions are from the Kanban Guide (edition 2025.5): throughput is the number of items finished per unit of time, cycle time is the elapsed time from started to finished, and work item age is the elapsed time from started to today.

Question you are asked Input you need Method What you say back
How long should one new item take? Cycle time of finished items Read percentiles of the cycle time list 85% of items finish in 9 days or fewer
When will these 45 items be done? Throughput per day or week Sample past days until the total reaches the backlog 85% chance by day 36
How much will be done by a date? Throughput per day or week Sample as many days as the date allows and add them up 85% chance of at least 17 items in 15 days
Will this item that is already open make it? Cycle times plus the item’s age Compare age with the cycle time list Of items that ran past 8 days, 80% finished by day 12

Illustrative example. Numbers come from the invented history in the next section.

The history behind every kanban forecasting example

The data below is invented for this post and labelled as such. It covers eight weeks, 40 working days, with 60 items finished. It includes 9 zero days and two 5-item days, because real boards have both. You will need the same two exports from your own board: the finish date of every item that finished, and its start date.

Week Mon Tue Wed Thu Fri Items finished
Week 1 1 1 1 0 0 3
Week 2 1 5 2 1 2 11
Week 3 1 2 0 1 4 8
Week 4 2 1 1 1 1 6
Week 5 1 1 4 0 2 8
Week 6 0 0 3 1 0 4
Week 7 1 3 0 2 5 11
Week 8 1 0 1 3 4 9
Total 60

Illustrative example. Items finished per working day, not data from any team.

The 60 items had cycle times from 1 to 22 days. The average is 6.6 days, but the 50th, 70th, 85th and 95th percentiles are 6, 7, 9 and 11 days, because a few slow items pull the average up. By Little’s Law, 1.5 items a day at 6.6 days implies about 10 items in progress at once (our arithmetic, not a measured WIP).

How to build a throughput forecast by hand: when will 45 items be done

One simulated future, then 10,000 of them
1
Write the history as a list
One number per working day: 1, 1, 1, 0, 0, 1, 5 and so on, 40 numbers in all.
2
Pick a day at random and add its number
Draw from the list with replacement. A drawn 0 is allowed and matters. The first eight draws of one run here were 1, 1, 3, 1, 0, 2, 1, 1.
3
Stop when the total reaches the backlog
That run reached 45 items on day 29. It is one possible future, not a prediction.
4
Repeat 10,000 times
A different run lands on a different day count each time. Keep every result.
5
Sort the results and read the percentiles
The 85th percentile is the smallest day count that at least 85% of runs finished within.

You can do this in a spreadsheet. Make one row per run. In each cell of the first block, enter =INDEX(history, RANDBETWEEN(1, 40)), where history is your list of daily counts. Make a second block of running totals, count how many running totals are still under 45 with COUNTIF, and add 1. That is the day the run finished. Copy the row down 1,000 times at least, paste values to freeze it, then use PERCENTILE or sort the column. A short script does the same in seconds.

Working days to finish 45 items, 10,000 simulated futures

Blue bars: runs that finished by the 85% line. Grey bars: the slower 15%.

20253035404550Working days to finish 45 itemsShare of runs50%: 3085%: 3695%: 39

Illustrative example. Sampled from the 40-day history above with a fixed random seed.

Confidence Working days About how many weeks What it means
50% 30 6.0 Even odds. Late as often as early
70% 33 6.6 Late about 3 times in 10
85% 36 7.2 Late about 1 time in 7. A common planning line
95% 39 7.8 Late 1 time in 20. Use for commitments with a penalty

Illustrative example. The average method, 45 items at 1.5 a day, gives 30 days. Only 51% of the simulated runs finished within 30 days.

The average is the 50th percentile mislabelled as a promise. The gap between 30 and 36 days comes from zero days and lulls, which an average spreads evenly and a simulation keeps.

How much by a date: the other half of kanban forecasting

In kanban forecasting a stakeholder often gives you the date and asks what fits. Reverse the stopping rule: draw 15 days, add them up, repeat, and read the percentiles from the other end. The 85% answer is the 15th percentile of the counts, the number that 85% of runs met or beat.

Items finished over the next 20 working days

The band shows where the middle 70% of simulated futures sit (15th to 85th percentile).

051015200102030Working days from todayItems finished282217Green: only 15% of runs did better than thisBlue dashed: the median runRed: 85% of runs did at least this well

Illustrative example. 10,000 runs, fixed seed. At day 15 the lines read 17, 22 and 28 items.

Confidence of finishing at least Items in 15 working days
50% 22 (the average, 15 days at 1.5 a day, lands here)
70% 19
85% 17 (quote this one)
95% 14

Illustrative example. Read upward: a higher confidence means a smaller promised count.

The band widens with every day, which is why kanban forecasting weakens the further out you look. Two weeks ahead is useful. Forty days ahead is a range.

Cycle time in kanban forecasting: what it can and cannot do

The Kanban Guide defines the service level expectation as a period of elapsed time plus a probability, with the example “85% of work items will be finished in eight days or less.” It says the SLE should be based on historical cycle time and, when no history exists, a best guess will do until there is enough. For our 60 items, the 85th percentile cycle time is 9 days, so the expectation reads: 85% of items finish in 9 days or less.

Use that number in two ways:

  • Set expectations for a new item. Quote the percentile.
  • Judge an item already in progress. In the history, 15 items ran past 8 days, and 12 of them finished by day 12 (80%). An item at age 8 therefore has about 4 in 5 odds of finishing by day 12, a rough read from only 15 items. Our post on work item aging shows how to act on it.
A common trap. Do not add up sampled cycle times to forecast a backlog. Summing 45 sampled cycle times gives an 85th percentile of 325 days here, about nine times the throughput answer, because the team works on about 10 items at once and the sum treats them as one-at-a-time. Cycle times describe how long one item takes. Throughput describes how fast the system finishes items.

How much history kanban forecasting needs

The Kanban Guide gives no minimum for kanban forecasting. So we measured it. We built an invented process with a known answer, drew 300 random histories of each length, and asked each for the 85% forecast for 45 items. The true answer is 36 working days. The table shows how far short histories can land.

History used 10th percentile of forecasts Median forecast 90th percentile of forecasts Spread (days)
5 days (1 wk) 23 36 65 42
10 days (2 wk) 25 36 59 34
20 days (4 wk) 28 36 49 21
40 days (8 wk) 30 37 44 14
80 days (16 wk) 32 36 42 10

Illustrative example. 300 histories per length, 1,000 runs each, fixed seeds. True 85th percentile: 36 days.

Spread of the 85% forecast by history length (days, lower is better)

Width between the 10th and 90th percentile of the forecasts. Illustrative example, from the experiment above.

5 days of history42
10 days of history34
20 days of history21
40 days of history14
80 days of history10

Our reading, not an official rule: with 5 or 10 days a forecast can miss by weeks. At 20 days the spread shrinks to 21 days, and at 40 days to 14. Aim for at least 20 to 40 working days of history from the same team on the same kind of work, and widen your range when you have less. A short recent window beats a long one from before the system changed.

Five pitfalls that break a kanban forecasting model

Pitfall What it does Number from our examples What to do
Trending data Old weeks drag a forecast toward a system that no longer exists Throughput rose from 1.1 to 2.0 a day. All 40 days: 85% at 34 days. Last 20 only: 25 Cut the window at the change. Re-baseline after a new WIP limit, team or work type
Batch arrival Items finish only on release days, so daily sampling misstates the spread Friday-only releases: daily sampling says 44 days, sampling whole weeks says 7 weeks (35 days) Sample per release or per week and answer in releases
Blocked items Blocked time is part of cycle time. Removing it makes the SLE optimistic Cycle time is elapsed time from started to finished, so waiting days count Keep blocked days in. Study them separately, see blocked items
Scope creep The backlog grows while you burn it down Backlog +10%: 40 days. +20%: 42. +30%: 45 (from 36) Measure how much new work arrives per week and add it before each run
Small samples and zero-heavy history Wide, unstable percentiles. Mostly zero days make the output swing 5 days of history: 85% forecasts ranged 23 to 65 days Say “range” not a date. Fix flow before forecasting

Illustrative example. Backlog 45 items at the start. All figures from seeded simulations on invented data.

A sixth rule sits under all five: a forecast holds only while the future resembles the past. Scrum.org’s January 2020 article on probabilistic forecasting says to re-examine the forecast when the team or its work changes materially. For the mechanics of keeping flow steady, read how to set WIP limits and how to read a cumulative flow diagram.

Reading and saying a percentile

Good kanban forecasting ends in a sentence a stakeholder can use. A percentile is a share of simulated futures, not a measure of accuracy. When someone hears “85% confidence by day 36,” say it plainly: in 85 of 100 futures like our history, the work is done by then, and in the other 15 it is later. Day 30 is the median, so the team misses it half the time.

Instead of Say Why
“It will be done on day 36.” “85% likely by day 36, 50% by day 30, and 95% by day 39.” A single date hides the spread
“We are 85% accurate.” “85% of simulated futures finished by then.” Accuracy is judged later, across many forecasts
A weekly kanban forecasting routine
1
Export the dates
Start and finish dates for your window, with the same definition of started and finished each week.
2
Check the window
Same team, same kind of work, no big change inside it.
3
Add new scope
Add items that arrived since last time to the backlog count.
4
Run and read
Run when and how many. Read the 50, 85 and 95 lines.
5
Record and score
Write the 85% forecast down. Next month, count how often reality landed inside it.
Free tool. The AgileFever flow metrics analyzer reads your start and finish dates and shows cycle time, throughput and aging, the inputs for every forecast here. For managers, see Kanban metrics training for managers. For why throughput replaces velocity, see Kanban velocity vs throughput.

Who should skip Monte Carlo for now

  • Teams with fewer than about 10 finished items. Use a best guess and label it as one, as the Kanban Guide allows.
  • Teams that finish almost nothing in most weeks, or changed team size, WIP limit or work type last month. Fix the flow or start a new baseline first.

Learn flow forecasting with a certified instructor

AgileFever sells Kanban Systems Improvement (KSI), a Kanban University course. Its published curriculum includes lead time distribution, demand patterns, bottlenecks and optimizing flow and predictability, which are the ideas behind this post. As listed on November 25, 2026, the list price is $1,200 or ₹27,999, before 18% GST for buyers in India. The product page lists the Team Kanban Practitioner course plus Kanban System Design, or the KMP 1 course, as the prerequisites.

Additional discounts are available. Contact us to know more.

For the exact definitions, read the Kanban Guide, edition 2025.5. For a book-length treatment, see Daniel Vacanti’s Actionable Agile Metrics for Predictability and When Will It Be Done?.

Questions people ask

What is Monte Carlo simulation in Kanban?

It turns your own history into a range of outcomes. You draw past days at random, say 10,000 times, and record each run. The percentiles of the results become your forecast, such as 85% by day 36.

How many data points do I need for Monte Carlo forecasting?

No official source sets a minimum. In our invented experiment, 5 to 10 days gave forecasts that could miss by weeks, while 20 to 40 working days narrowed the range sharply. Use 20 to 40 days from one team and work type.

Should I forecast with cycle time or throughput?

Use cycle time for how long one item should take and for items already open. Use throughput for a backlog or a date. Do not add up sampled cycle times for a backlog, because items run in parallel.

What does the 85th percentile mean?

It means 85% of the simulated futures finished by that point and 15% finished later. In our example, 85% of runs finished 45 items within 36 working days. It does not mean the forecast is 85% accurate.

How often should I re-run a forecast?

Weekly, and whenever scope or the team changes. Add new items to the backlog count each time and record each 85% forecast, so you can check later how often reality landed inside it.

Can AI do my Kanban forecasting?

AI can draft the script or explain the output, but the date should come from your own flow data. A model that guesses a date does not use your distribution and cannot be reproduced.

Contact Us

    By checking the box, you consent to receive registrations, class reminders, updates, support text messages from AgileFever at the provided number. Message and data rates may apply. Message frequency varies (typically 1–2 msgs/week). To end messaging from us, you may always reply with STOP. You may also reply with HELP for more information. Check Privacy Policy and Terms & Conditions.