cumulative flow diagram

How to Read a Cumulative Flow Diagram in 10 Minutes

Table of Contents

Short answer. Read a cumulative flow diagram three ways. Vertical distance between two lines is the work in progress at that date. Horizontal distance between the line for started work and the line for finished work is how long an item took. Slope of the finished line is throughput. In the invented example below, the team held 8 items in progress and finished 5 a week, so items took 1.6 weeks. After week 4 the finished line stalled for two weeks, in-progress work climbed to 20, and one item took 3.9 weeks.

Written by the AgileFever editorial team. Facts checked on November 17, 2026 against the official pages of the organizations named in this post. AgileFever sells training for some of the topics covered here, and we say so wherever it applies. Metric definitions are from the Kanban Guide (version 2025.5). The example data in this post is invented and labelled as such.

A cumulative flow diagram, usually shortened to CFD, shows queues forming before anyone complains about them. Most guides say the bands should look parallel and stop there. This post gives you three readings you can take with a ruler, checked against a worked example. For the control chart and the scatterplot, read our Kanban reports guide as well.

What a cumulative flow diagram shows

A cumulative flow diagram plots, for every day or week, how many work items have ever reached each stage of your workflow. Time runs left to right. The vertical axis is a running count of items. Each colored band is the gap between two lines, and each line is one stage boundary.

Because the counts are cumulative, the lines never fall as work moves forward. An item that left the Ready column is still counted as having reached it. That is why a band’s height tells you how many items are sitting in that stage right now, and why the top line is the total that has ever arrived. Atlassian’s Jira Cloud documentation describes the same logic (checked November 17, 2026).

The example below is invented and runs through the whole post. A team moves work through four stages: Ready, In progress, In test and Done. The table gives the cumulative count at the end of each week.

Week Arrived (top line) Started Reached test Done Items in progress (started minus done)
0 20 12 7 4 8
1 26 17 12 9 8
2 32 22 17 14 8
3 38 27 22 19 8
4 44 32 27 24 8
5 50 37 31 27 10
6 56 42 34 27 15
7 62 47 36 27 20
8 68 52 38 33 19

Illustrative example, not real team data. Counts are cumulative at the end of each week.

How to read a cumulative flow diagram: three measurements

Here is the same data as a chart, with a vertical bracket, a horizontal arrow and the slope of the green edge marked.

Cumulative flow diagram for an invented team, weeks 0 to 8

The bracket at week 7 measures work in progress. The dashed arrow measures how long item 30 took.

010203040506070Wk 0Wk 1Wk 2Wk 3Wk 4Wk 5Wk 6Wk 7Wk 8ReadyIn progressIn testDoneWeeks 0 to 4: steadyWeeks 4 to 8: test queue growsWIP20Item 30: 3.9 weeksCumulative items

Illustrative example, not real team data. Plotted from the table above.

Vertical distance is work in progress

The Kanban Guide (version 2025.5, updated May 1, 2025) defines work in progress as the number of work items started but not finished. On the chart, that is the vertical gap between the Started line and the Done line. At week 7 in the example it is 47 minus 27, which is 20 items. The Ready band is not part of it. Items waiting in Ready have not started, so by the Guide’s definition they are not work in progress. Many articles add every band except Done and call that WIP. If your team has a commitment point, measure from it.

Horizontal distance is time in system

Pick an item number on the vertical axis and move sideways. The distance between where the Started line reaches that number and where the Done line reaches it is the item’s cycle time. The Guide defines cycle time as the elapsed time between when a work item started and when it finished. In the example, item 14 started at week 0.4 and finished at week 2.0, so it took 1.6 weeks. Item 30 started at week 3.6 and finished at week 7.5, so it took 3.9 weeks.

Measure from the Arrived line instead and you get time since the item entered the board, which many teams call lead time. The Guide does not define lead time, so say which one you mean. This reading is exact only when items finish in the order they started. If items overtake each other, treat it as an average.

Slope is rate

A steeper line means more items crossing that boundary each week. The slope of the Done line is throughput, which the Guide defines as the number of work items finished per unit of time. In weeks 0 to 4 the Done line rises 5 items a week. In weeks 5 to 7 it is flat: zero. If you want to know why we prefer throughput to velocity for this, read Kanban velocity vs throughput.

What you want Where to look How to measure Definition
Work in progress Vertical gap, Started line to Done line Read both lines at one date and subtract Items started but not finished (Kanban Guide)
Cycle time of one item Horizontal gap, Started line to Done line Find the item number on both lines, subtract the dates Elapsed time from start to finish (Kanban Guide)
Throughput Slope of the Done line Items added to Done divided by weeks elapsed Items finished per unit of time (Kanban Guide)
Queue before the commitment point Height of the Ready band Arrived minus Started Not WIP: these items have not started

Definitions quoted or paraphrased from the Kanban Guide, version 2025.5, checked November 17, 2026. The Guide does not name the cumulative flow diagram; the readings follow from its definitions.

Worked example: from the chart to a diagnosis

Take the weeks 0 to 4 first. Started minus Done is 8 in every week. The Done line rises 5 a week: 4 at week 0, 24 at week 4, so 20 items in 4 weeks. Every band keeps a constant height and the lines run parallel. That is what a steady flow looks like.

Now weeks 4 to 8. The Done line is flat at 27 for weeks 5, 6 and 7, then jumps to 33 at week 8 (a batch of 6). Meanwhile the Started line keeps climbing 5 a week, so work in progress goes 10, 15, 20 and 19. The In test band grows from 3 items to 9 at week 7, and the In progress band grows from 5 to 14. Items are leaving development faster than testing is finishing them, and the team keeps starting new ones anyway.

The chart cannot say why testing slowed. That is a question for the team. It does show when the slowdown began, which column holds the queue and how many items it affects.

The Ready band grows from 8 to 16 items because 6 items arrive each week and the team starts 5. That backlog is not WIP, but it is a signal to talk to whoever feeds the board.

Checking the example against Little’s Law

Little’s Law says average work in progress equals average throughput times average cycle time. Our post on Little’s Law covers the formula. Todd Little, chairman of Kanban University, draws a cumulative flow diagram in Kanban University’s Little’s Law slides and marks approximate average WIP, lead time and delivery rate on it, with the relation lead time = WIP / delivery rate.

The slides also state the condition: the system must not be trending. Items entering and leaving must be similar in number, and the average age of items in progress must not be rising or falling.

Window Average WIP Throughput WIP divided by throughput Measured on items Steady?
Weeks 0 to 4 8 5 a week 1.6 weeks Items 14 and 20: 1.6 weeks each Yes: the sideways gap is constant
Weeks 4 to 8 14.4 2.25 a week 6.4 weeks Items 30 and 32: 3.9 and 3.8 weeks No: WIP rises from 8 to 19 and Done stalls

Illustrative example, not real team data. Average WIP for weeks 4 to 8 is the mean of the five weekly values 8, 10, 15, 20 and 19. Throughput is 9 items finished (24 to 33) in 4 weeks.

In the steady window the law and the sideways measurement agree at 1.6 weeks. In the second window they do not, which tells you the system is not steady and averages mislead. Use the law where the lines run parallel, and the picture where they do not.

Cumulative flow diagram patterns and what to do

Three shapes to recognise

Green is Done, blue is the middle stage, purple is the stage before it. Each panel shows nine weekly points.

BulgeMiddle band widens, thendrains: a queue clearedFlat bandDone line stalls for weekswhile starts continueStaircaseDone jumps in batches:work released together

Illustrative example, not real team data.

Pattern What you see What it often means First thing to do
Bulge A band widens, then narrows A queue formed and was cleared Find the week it started and ask what changed: people away, a release freeze, a blocked dependency
Flat band or flat Done line A line stops rising while the line above it keeps climbing Work enters a stage but nothing leaves it Stop starting new work and swarm the stuck stage. Check for blockers and for a missing handoff
Staircase Done rises in jumps, flat between them Work is released in batches, or items are moved to Done in bulk Check the release rhythm. If the jumps are bulk edits in the tool, the dates are wrong, and cycle time reads long
A wide band is not always a problem. Planned batching, such as an end-of-month release, makes a band widen and then drop by design. A band that widens for weeks with no recovery is the one to chase.

Once you know which column holds the queue, the next step is a limit on it. Our guide to setting WIP limits walks through the method. In this invented example, WIP held at 8 in the steady weeks, so a first limit near 8 would have stopped new starts in week 5, when WIP reached 10.

Read a cumulative flow diagram in 10 minutes

A ten-minute routine for a weekly review
1
Minute 0 to 1: set the window
Choose 8 to 12 weeks. Confirm which column counts as Done.
2
Minute 1 to 3: compare slopes
Look at the arrival line, the Started line and the Done line. Are they roughly parallel? If the top two climb faster than Done, work is piling up.
3
Minute 3 to 5: measure WIP
Take the vertical gap from Started to Done at three dates. Compare it with your WIP limit, if you have one.
4
Minute 5 to 7: measure time
Pick three items, one early, one middle, one recent. Read the sideways gap for each and compare it with your promise to customers.
5
Minute 7 to 9: find the odd band
Name the column that is bulging, flat or stepping. Write down the date it began.
6
Minute 9 to 10: record one action
Write one action and one question for the team. Check Little’s Law only if the window was steady.

Reading the cumulative flow diagram in Jira

If your team uses Jira, the report is on the board’s Reports menu. These points come from Atlassian’s Jira Cloud documentation page on the cumulative flow diagram, checked November 17, 2026.

Jira behaviour What it means for your reading What to do
Horizontal axis is time, vertical axis is work items, each band is one board column Your bands are your board columns, not your real workflow, if the two differ Keep columns close to real stages before you trust the picture
To Do is the left-most column and Done is the right-most column Anything in the right-most column counts as finished Keep cancelled or rejected items out of that column, or throughput reads high
The report shows data for the whole life of the space by default Old history can hide a recent problem Use the date filter to show the last 8 to 12 weeks, or one sprint

Mistakes that make a cumulative flow diagram misleading

  • Counting the Ready column as WIP. The Guide counts items started but not finished. Items still waiting have not started.
  • Treating every wide band as a bottleneck. A planned batch looks the same for a few weeks. Check whether the Done line recovers.
  • Reading the sideways gap as a promise. It is exact only if items finish in start order. For promises, use percentiles from a scatterplot. See Kanban reports.
  • Applying Little’s Law to a trending window. The slides’ condition is no trend in arrivals, departures or item age. The second window in the example breaks it.

To pull cycle time, throughput and WIP from your own tracker export and compare them with what you read off the chart, use the free Flow Metrics Analyzer. It computes them from the same dates a cumulative flow diagram uses. For more on the metrics themselves, see key flow metrics.

Where AgileFever fits

We teach Kanban University courses, so weigh our view accordingly. This post is enough to read the chart. The harder part is acting on it: choosing a WIP limit, changing policies at a stage and agreeing a service level expectation. That is where we sell Kanban Systems Improvement (KSI). The course page describes it as a sequel to KMP1 that covers pull systems, queuing theory and flow. It is listed at $1,200 per seat for US buyers, with a batch on Nov 21 to Nov 22, 2026, as listed on November 17, 2026. Rupee prices on the page are before the 18% GST we add at checkout for buyers in India.

Additional discounts are available. Contact us to know more.

Questions people ask

What is a cumulative flow diagram?

A cumulative flow diagram is a stacked area chart that counts, for each date, how many work items have reached each stage of a workflow. Time is on the horizontal axis and the cumulative item count is on the vertical axis. Each band is one stage, so band height shows how many items are in that stage.

How do you read WIP on a cumulative flow diagram?

Take the vertical distance between the line for started work and the line for finished work at a given date. The Kanban Guide defines work in progress as items started but not finished, so do not include items still waiting before the start. In the invented example, week 7 gives 47 minus 27, which is 20 items.

How do you read cycle time on a cumulative flow diagram?

Choose an item number, find the date the started line reaches it and the date the finished line reaches it, then subtract. The result is that item’s cycle time. It is exact only when items finish in the order they started; otherwise treat it as an average for the band.

What does a flat band mean on a cumulative flow diagram?

A flat line means no items crossed that boundary in that period. If the Done line is flat while the lines above it still rise, work is entering the system but nothing is finishing. Look for blockers, a missing handoff or a stuck stage, then check whether the line recovers.

Is a cumulative flow diagram the same as a burnup chart?

No. A burnup chart shows completed work against total scope as two lines. This chart shows every stage as a band, so you can also see where work waits.

How does Little’s Law relate to a cumulative flow diagram?

Little’s Law says average WIP equals average throughput times average cycle time. On the chart, WIP is the vertical gap, throughput is the slope of the Done line and cycle time is the horizontal gap. It holds on a steady window, where arrivals and departures are similar and item age is not trending.

Contact Us

    By checking the box, you consent to receive registrations, class reminders, updates, support text messages from AgileFever at the provided number. Message and data rates may apply. Message frequency varies (typically 1–2 msgs/week). To end messaging from us, you may always reply with STOP. You may also reply with HELP for more information. Check Privacy Policy and Terms & Conditions.